Toxics Cleanup Program

Bellingham Bay Cleanup Sites

Marine Services NW Holly Street Landfill Whatcom Waterway Holly Street R.G. Haley Cornwall Avenue Landfill

Cleanup Progress Initial
Site Assess-ment
Agreed Order Draft RI/FS Consent Decree Project Design and Permit Construct Long-Term Monitoring
Central Waterfront X X O 2009 2010 2010 2012
Cornwall Avenue Landfill X X O 2009 2010 2010 2012
Eldridge Avenue Landfill X 2009 TBD TBD TBD TBD TBD
Georgia-Pacific West X 2009 2010 2011 2012 2013 2014
R. G. Haley X X O 2010 2010 2011 2013
Harris Avenue Shipyard X X 2012 2013 2014 2015 2016
Holly St Landfill X X X X X X O
I&J Waterway X X O 2010 2011 2012 N/A
Little Squalicum Park X X O 2009 2010 2011 2011
Marine Services  NW X 2011 2012 2012 2013 2014 2015
S. State St. Manufactured Gas Plant (Formerly Blvd. Park) X 2009 2011 2012 2012 2013 2014
Weldcraft Steel & Marine X X O 2010 2010 2010 2011
Whatcom Waterway X X X X O 2010 2014
X = Completed
O = In progress