SITE DESCRIPTION
The
KB Alloys Site is an aluminum master alloy production operation. A Phase I
Environmental Assessment conducted at the site in 1989 determined that
polychlorinated biphenyl (PCB) containing capacitors at the site had released
PCBs inside the facility. Several steps were taken to remediate PCB-containing
materials in the facility. A small amount of PCB-contaminated soil was detected
below the concrete surface. This soil could not be removed without risking
structural damage to the facility. In addition, a small amount of contamination
remained ingrained in areas of concrete that could not be removed without
risking structural damage to the facility. Following remedial actions, a new
layer of surface concrete was placed in the cleanup area and the cleaned and
sandblasted surfaces were sealed and repainted. All materials removed as part
of this remedial action were disposed of as PCB-containing waste. It was
determined that these remedial activities were protective of groundwater and of
human health. No further remedial actions were required at the site.
SITE DOCUMENTS
Site Documents
Related Information
Additional Resources
|
|
SITE INFORMATION
Facility Site ID:
# 71442764
Location:
Malaga, Chelan County
Contact:
Jeff Newschwander Site Manager
509/454-7842Frosti
Smith
Public Involvement Coordinator
509/454-7841
Status:
Remedial Action and all other activities completed
|