Publication Summary

Title

Quality Assurance Project Plan: Groundwater Assessment Program Pilot Study, Phase 2

Month-Year PublishedJanuary 2004
Online Availability
View this publication in Acrobat PDF format
3053 kilobytes,  requires version 4.0 or later of Adobe Acrobat Reader Software  get Acrobat Reader
Short Description

This is the Quality Assurance Project Plan for the study, Groundwater Assessment Program Pilot Study Phase 2

(Also see abstract below)
Publication Number04-03-102
Author(s)Pitz, C.
Print Availability
Request from the program.
Number of pages 36 pp.
Keywords assessment, environmental, groundwater, plan, quality assurance, quality assurance project plan, study
Related Publications TitleRelationship    
Quality Assurance Project Plan: Groundwater Assessment Program Pilot Study, Phase 1similar topic
Washington State Groundwater Assessment Program: Hydrology and Quality of Groundwater in the Centralia-Chehalis Area Surficial Aquifersimilar topic
Abstract Long Description

In response to concerns regarding the absence of a systematic, state-level approach to measuring and describing ambient groundwater conditions, a pilot test of a Washington Department of Ecology (Ecology)-based groundwater assessment program was recommended. The program design proposed for trial is intended to provide comparable procedures for the collection of baseline information about groundwater and hydrogeologic conditions at a basin or subbasin scale. Conducting a pilot study will allow evaluation and refinement of the technical methods and schedule, staff, and budget requirements of the proposed assessment approach. The lessons learned during the pilot study will be instrumental in the agency′s decision whether to pursue and dedicate resources to a longer-term state program.

In October 2003, a Quality Assurance Project Plan (QA Project Plan) was published describing field activities being conducted during the pilot study under the terms of a U.S. Environmental Protection Agency (EPA) grant (Phase 1). This current plan was prepared to describe the field activities for the remaining portion of the pilot study (Phase 2).

Link to EIM data for User Study ID GAP0001