| Title | Treetop, Wenatchee Wastewater Treatment Plant, Class II Inspection. | |||
| Month-Year Published | June 1989 | |||
| Online Availability |
516 kilobytes, requires version 4.0 or later of Adobe Acrobat Reader Software get Acrobat Reader
| |||
| Short Description |
A Class II inspection was conducted at the Treetop, Wenatchee, wastewater treatment plant on March 15-16, 1988. The plant was in compliance with all permitted parameters at the time of the inspection. (Also see abstract below) | |||
| Publication Number | 89-e45 | |||
| Author(s) | Reif, D. | |||
| Print Availability |
Not maintained in stock. Copy must be made from archive version.
| |||
| Number of pages | 11 pp. | |||
| Keywords | Inspection, site investigation, treatment, waste, wastewater, wastewater treatment plant | |||
| Subject Waterbodies |
| |||
| Abstract | Long Description |
A Class II inspection was conducted at the Treetop, Wenatchee, wastewater treatment plant on March 15-16, 1988. The plant was in compliance with all permitted parameters at the time of the inspection. Flows and loadings were well below designed limits, and effluent loadings also far below NPDES permit limits. Intermediate process sampling procedures, as required in the permit, were found to be helpful in understanding process dynamics. Some of the sample splits did not compare well. Based on this, and the findings of the laboratory procedures survey, several recommendations are made, including further lab sample comparisons. Other recommendations include a review of Treetop′s preventive maintenance program and spare parts inventory. |
||