Puyallup and White Rivers Dissolved Oxygen and Temperature Data Summary Report08-03-013May 2008
Clarks Creek Watershed Fecal Coliform TMDL07-10-110May 2008
American Plating Post-Interim-Action Groundwater Monitoring Results, April and September, 200708-03-004February 2008
Condition of Coastal Waters of Washington State, 2000-2003: A Statistical Summary07-03-051December 2007
Addendum to the Quality Assurance Project Plan for the American Plating Post-Interim Action Monitoring.04-03-105ADDFebruary 2007
American Plating Post-Interim-Action Groundwater Monitoring Results, May and September, 200607-03-005February 2007
Quality Assurance Project Plan: Puyallup River Watershed Fecal Coliform Bacteria Total Maximum Daily Load Study06-03-115December 2006
Quality Assurance Project Plan: Puyallup and White Rivers Temperature and Dissolved Oxygen Monitoring06-03-204August 2006
South Puget Sound Verification of 303(d) Listings for Chemical Contaminants in Fish and Shellfish06-03-026July 2006
South Prairie Creek Bacteria and Temperature Total Maximum Daily Load (Water Cleanup Plan): Detailed Implementation Plan06-10-018July 2006
Lake Tapps (Pierce County) Monitoring, Final Data Report06-03-006January 2006
Upper White Watershed Sediment and Temperature Total Maximum Daily Load (Water Cleanup Plan) for Aquatic Habitat: Detailed Implementation Plan05-10-038January 2006
American Plating Post-Interim-Action Groundwater Monitoring Results, March and August 200506-03-005January 2006
Progress on Watershed Planning and Setting Instream Flows05-11-038December 2005
Quality Assurance Project Plan: South Puget Sound Fish and Shellfish Tissue Verification of 303(d) Listings05-03-116November 2005
Changes and Trends in Puget Sound Sediments: Results of the Puget Sound Ambient Monitoring Program, 1989-200005-03-024August 2005
Temporal Monitoring of Puget Sound Sediments: Results of the Puget Sound Ambient Monitoring Program, 1989-200005-03-016July 2005
Puyallup and White Rivers Temperature and Dissolved Oxygen July - November 2004 Monitoring Report05-10-053June 2005
Marine Fueling and Oil Transfer Practices for Covered Vessels and Ships in Washington04-08-005December 2004
American Plating Post-Interim-Action Groundwater Monitoring Results, February and August 200404-03-052November 2004
Upper White Watershed Temperature Data Report: 1989 to 200304-10-061September 2004
Quality Assurance Project Plan: Lake Tapps Monitoring04-03-204July 2004
Quality Assurance Project Plan: American Plating Post-Interim Action Monitoring04-03-105March 2004
Chemical Contamination, Acute Toxicity in Laboratory Tests, and Benthic Impacts in Sediments of Puget Sound: A summary of results of the joint 1997-1999 Ecology/NOAA survey03-03-049November 2003
Upper White Watershed Spring Chinook Redd, Scour, and Cross-Section Assessments: 1995 - 200103-10-071August 2003
Mt. Baker Snoqualmie National Forest Upper White Watershed Sediment and Temperature TMDL for Aquatic Habitat: Submittal Report03-10-032June 2003
South Prairie Creek Bacteria and Temperature Total Maximum Daily Load (Water Cleanup Plan): Submittal Report03-10-055June 2003
South Prairie Creek Bacteria and Temperature Total Maximum Daily Load Study03-03-021June 2003
Focus on White River pH Water Cleanup Plan03-10-026March 2003
Focus on South Prairie Creek03-10-024March 2003
Effectiveness Monitoring for Dioxin Total Maximum Daily Loads in Western Washington03-03-002January 2003
Quality Assurance Project Plan: Lower White River Temperature Study03-10-028January 2003
Mobilization and Impacts of Arsenic Species and Selected Metals on a Wetland Adjacent to the B&L Landfill, Milton02-03-053November 2002
Results and Recommendations from Monitoring Arsenic Levels in 303(d) Listed Rivers in Washington02-03-045October 2002
Sediment Quality in Puget Sound: Year 3, Southern Puget Sound02-03-033July 2002
Quality Assurance Project Plan: Mobilization and Impacts of Arsenic Species and Selected Metals on a Wetland Adjacent the B&L Landfill, Milton, Washington02-03-086April 2002
PCBs in Sediments at Selected Sites in Puget Sound02-03-003February 2002
River and Stream Ambient Monitoring Report for Water Year 200001-03-042December 2001
Contaminants Associated with Settling Particulate Matter and Bottom Sediments at Two Marinas in Thea Foss Waterway01-03-023June 2001
Focus Sheet: Upper White River at Risk: First Steps Toward Restoration01-10-038June 2001
Re-Evaluation of Copper Impact from Wilkeson Wastewater Treatment Plant on Wilkeson Creek.01-03-021May 2001
Quality Assurance Project Plan: South Prairie Creek Total Maximum Daily Load Phase II Evaluation01-03-064January 2001
Quality Assurance Project Plan: South Prairie Creek Total Maximum Daily Load, Phase 1 Assessment00-03-081August 2000
Water Quality Assessments of Selected Lakes within Washington State: 199700-03-009March 2000
Review Draft: Assimilative Capacity Study for Nutrient Loading in the Lower White River00-03-001December 1999
River and Stream Ambient Monitoring Report for Water Year 199799-332August 1999
Return to Clean: Washington State's source-control efforts cut metals concentrations in Commencement Bay by a factor of 10 -- IN Water Environment and Technology, June 1999, p. 51-57.99-334June 1999
Metals Concentrations in Commencement Bay Waterways During 1997 - 199899-308February 1999
1998 Sediment Trap Monitoring of Suspended Particulates in Stormwater Discharges (Thea Foss)98-336December 1998
Washington State Marine Water Quality in 1996 and 199798-338December 1998
Marine Sediment Monitoring Program II - Distribution and Structure of Benthic Communities in Puget Sound - 1989-199398-328September 1998
Marine Sediment Monitoring Program I - Chemistry and Toxicity Testing. 1989-199598-323August 1998
River and Stream Ambient Monitoring Report for Wateryear 199698-317June 1998
Upper White River Spring Chinook Habitat Assessment Study98-304March 1998
Stormwater Sediment Trap Monitoring of Discharges to Thea Foss Waterway97-322May 1997
Puyallup Basin Treatment Plant Metals Survey97-303April 1997
Washington State Marine Water Quality in 1994 and 199597-316April 1997
Water Quality Assessments of Selected Lakes within Washington State - 199497-307February 1997
River and Stream Ambient Monitoring Report for Wateryear 199596-355December 1996
City of Sumner Wastewater Treatment Plant Class II Inspection, April 22-24, 199696-350November 1996
Commencement Bay Sediment Trap Monitoring Program96-315April 1996
Washington State Pesticide Monitoring Program: Pesticides and PCBs in Marine Mussels, 199596-301March 1996
Lake Water Quality Assessment Program, 199396-3041996
Revised Continuous Simulation of Ammonia WLAs during November-April for the City of Enumclaw NPDES Permit. Memo to Kathy Cupps.95-e14September 1995
River and Stream Ambient Monitoring Report for Wateryear 199495-349September 1995
Metals Concentrations in Rivers and Streams Dropped from the 1994 Section 303(d) List95-352September 1995
Continuous Simulation of Ammonia WLAs for the City of Enumclaw NPDES Permit. Memo to Kathy Cupps August 14, 1995.95-e20August 1995
Sound Refining Company Class II Inspection, July 8, 199495-337July 1995
Results of Intertidal Sediment Sampling at the J. M. Martinac Facility on Thea Foss Waterway, Memo to Dom Reale, Southwest Regional Office.95-e11June 1995
Water Quality Impacts from Dairies in Washington State: A Literature Review95-326June 1995
Marine Water Column Ambient Monitoring Program: Wateryear 1995 Long-Term Monitoring Implementation Plan95-324May 1995
1994 Statewide Water Quality Assessment Lakes Chapter - Companion Document to WA State 305(b)95-311February 1995
Puyallup - White Watershed Initial Assessment95-0081995
Puyallup-White Watershed Assessment Summary95-1561995
Marine Water Column Ambient Monitoring Program: 199394-210December 1994
Zinc, Copper, and Cadmium Concentrations in Four Washington Rivers94-58October 1994
River and Stream Ambient Monitoring Report for Wateryear 199394-158September 1994
Addendum to the 1993 Puyallup River TMDL Report (Pub #96-326)94-e36July 1994
Puget Sound Ambient Monitoring Program, Marine Sediment Monitoring Task Annual Report 199194-93June 1994
Marine Sediment Monitoring Program Progress Report94-e28June 1994
Effectiveness of Forest Road and Timber Harvest Best Management Practices with Respect to Sediment-Related Water Quality Impacts, Interim Report No. 294-67May 1994
Freshwater Ambient Monitoring Report for Wateryear 199294-70May 1994
Lake Water Quality Assessment Program, 1991-199294-46April 1994
Evaluation of Thea Foss Waterway Storm Drain Data94-e391994
Puget Sound Ambient Monitoring Program 1992: Marine Sediment Monitoring Task Annual Report 199293-87October 1993
Freshwater Ambient Monitoring Report for Wateryear 199193-75September 1993
Spacial and Temporal Trends in Contaminant Levels in Settling Particulate Matter: Thea Foss Water (Commencement Bay) - June 1989 to November 199293-e44August 1993
Occidental Chemical Corporation Class II Inspection, September and December 199293-e58August 1993
Puyallup River Total Maximum Daily Load for Biochemical Oxygen Demand, Ammonia, and Residual Chlorine (This is a summary of 96-326, a 1993 report with the same title.)96-326aJuly 1993
A Summary of Priority Pollutant Data for Point Sources and Sediment in Inner Commencement Bay: A Preliminary Assessment of Data and Considerations for Future Work Part 4. Sitcum Waterway.83-e21July 1993
Marine Water Column Ambient Monitoring Program: Wateryear 1992 Data Report, Final Report.93-41June 1993
Effectiveness of Forest Road and Timber Harvest Best Management Practices with Respect to Sediment-Related Water Quality Impacts, Interim Report No. 194-27June 1993
Kaiser Aluminum Corporation, Tacoma, Class II Inspection - April 5-6, 199393-e57April 1993
Sonoco Products Company (Sumner Mill), June 2-3, 1992, Class II Inspection93-e22March 1993
Marine Water Column Ambient Monitoring Program: Annual Report for Wateryear 1991, Final Report.93-13February 1993
Lake Water Quality Assessment Project, 199092-1241993
Relative Dispersion of Water Masses Near Department of Ecology Long-Term Monitoring Stations in Puget Sound Model93-e011993
Spatial and Temporal Trends in Contaminant Levels in Settling Particulate Matter: Hylebos Waterway (Commencement Bay) - July 1990 to November 199192-e52December 1992
PCB Results of the Sediment Trap Samples near General Metals. Memorandum to Mohsen Kourehdar, Southwest Regional Office.92-e49November 1992
Effectiveness of Forest Road and Timber Harvest Best Management Practices with Respect to Sediment-related Water Quality Impacts, Progress Report92-e55October 1992
Marine Water Column Monitoring Program Annual Data Report for Wateryear 199092-77August 1992
Effectiveness of Washington's Forest Practice Riparian Management Zone Regulations for Protection of Stream Temperature92-64July 1992
Puget Sound Ambient Monitoring Program, Marine Sediment Monitoring Program: Annual Report 199092-47May 1992
Spatial and Temporal Trends in Contaminant Levels Associated with Settling Particulate Matter in Sitcum Waterway (Commencement Bay) July 1990 to June 199192-e51May 1992
Marine Water Column Ambient Monitoring Plan: Final Report92-23April 1992
Timber/Fish/Wildlife Ecoregion Bioassessment Pilot Project92-631992
Simpson Tacoma Kraft Company February 1991 Class II Inspection Report92-e381992
Lake Water Quality Assessment Project, 198991-60November 1991
Cascade Pole Company (Tacoma) - Aborted Stormwater Runoff Class II Inspection Attempts; Lessons Learned and Suggested Changes. Memo to Greg Cloud.91-e17September 1991
Quality of Salmonid Hatchery Effluents during a Summer Low-Flow Season. Article in Transactions of the American Fisheries Society 120:43-51, 1991.91-e321991
Burlington Class II Inspection Report - March 28-29, 1989. Memo to Dave Wright.90-e24October 1990
Tacoma Central Wastewater Treatment Plant Class II Inspection, June 26-28, 198990-e01June 1990
U.S. Oil and Refining Company Class II Inspection, June 13-14, 1989. Memo to Kim Anderson.90-e28May 1990
Edmonds Wastewater Treatment Plant Class II Inspection, April 17-19, 198990-e00May 1990
Use of Sediment Traps to Monitor Contaminant Flux to City Waterway Sediments: Interim Report90-e59March 1990
Lilyblad Class II Inspection Report, December 29-30, 198890-e261990
Weyerhaeuser, Enumclaw Class II Inspection. Memo to Richard Koch.89-e20December 1989
Enumclaw Class II Inspection Report, October 4-5, 1988.89-e16August 1989
Pennwalt Class II Inspection Report.89-e15April 1989
Quality and Fate of Fish Hatchery Effluents During the Summer Low Flow Season89-171989
Puyallup Wastewater Treatment Plant Class II Inspection--January 19-20, 1988.88-e11May 1988
An Investigation of Stormwater and Effluent Discharge from the Boeing Company Facility in Auburn, January 1987.87-e16December 1987
Metals Concentrations in Asarco Discharges and Receiving Waters Following Plant Closure.87-e34October 1987
Effects of Infiltration and Inflow on Wilkeson Wastewater Treatment Plant: Findings of a Limited Class II Inspection and Receiving Water Study.87-e22June 1987
Investigation of Stormwater Discharges to Wheeler Osgood Waterway.87-e33May 1987
An Investigation into Potential Sources of PCB Contamination in Hylebos Waterway.87-e35March 1987
Enumclaw Sewage Treatment Plant/Farman Brothers Pickle Company Class II Inspection, August 19-20, 1986. Memo to Gary Brugger.87-e10February 1987
Investigation of 4-Methylphenol in Bottom Sediments from Log Rafting Areas of Commencement Bay, Washington.87-e281987
Results of PCB Analysis on Sediment Samples from General Metals. Memo to Tom Eaton.86-e30October 1986
Plan for Investigation of PCB Sources in Hylebos Waterway. Memo to Dave Bradley.86-e19July 1986
Orting Class II Inspection. Memo to Darrel Anderson.85-e03July 1985
Completion Report on WQIS Project 4 for the Commencement Bay Nearshore/Tideflats Remedial Investigation: Sources of Sediment Contamination in Sitcum Waterway, with Emphasis on Ores Unloaded at Terminal 7. Memo to Jim Krull.85-e27April 1985
Completion Rpt WDOE Proj 5 (Part 3) for the Commencement Bay Nearshore/Tideflats Remedial Investig'n: Aromatic Hydrocarbons & Other Organic Compounds in GW Beneath D St Petroleum Storage Facilities & in Nearby City Waterway Sediments. Memo to Jim Krull.85-e161985
Completion Report on WQIS Project 2 for the Commencement Bay Nearshore/Tideflats Remedial Investigation: Metals Concentrations in Water, Sediment, and Fish Tissue Samples from Hylebos creek Drainage, August 1983 - September 1984.85-e171985
Completion Report on WQIS Project 1 for the Commencement Bay Nearshore/Tideflats Remedial Investigation: Assessment of Log Sort Yards as Metal Sources to Commencement Bay Waterways, November 1983 - June 1984.85-e261985
Completion Report on WQIS Project 5 (Part 1) for the Commencement Bay Nearshore/Tideflats Remedial Investigation: Priority Pollutants and Other Contaminants in City Waterway Storm Drains September-November 1983. Memo to Jim Krull.84-e21December 1984
Notification that WDOE Project No. 3 ("Routine Monitoring of Major Point Sources") for the Commencement Bay Nearshore/Tideflats Investigation is Completed. Memo to Jim Krull.84-e15August 1984
Organics Analysis of B&L Leachate. Memo to Greg Cloud.84-e16July 1984
Organics Data on Kaiser Ditch Water Samples. Memo to Roger Stanley.84-e17July 1984
Results of Priority Pollutant Analysis on Water and Sediment Samples at the Occidental and Pennwalt Facilities, Hylebos Waterway, April 1984. Memo to Frank Monahan.84-e20July 1984
Data on Leachate from the B & L Woodwaste Landfill. Memo to Frank Monahan.84-e36July 1984
Results of Organics Analysis on U.S. Oil Spill Samples. Memo to Jim Krull.84-e35July 1984
Appendices for: Completion Rpt WDOE Proj 5 (Part 3) for the Commencement Bay Nearshore/Tideflats Remedial Investigation: Aromatic Hydrocarbons & Other Organic Compounds in GW Beneath D St Petroleum Storage Facilities & in Nearby City Waterway Sediments85-e16appMay 1984
Chemicals in the Morningside Drain Discharge to Hylebos Waterway. Memo to Tom Eaton.84-e13May 1984
Comments on the Reapplication for a 301(h) Marine Waiver by the City of Tacoma for the North End Wastewater Treatment Plant. Memo to Carol Fleskes.84-e14April 1984
Results of Priority Pollutant Analyses on Water and Sediment Samples Collected January17, 1984, from the Blair Waterway Tote Facility Dredge Spoils Crib, Tacoma. Memo to Tom Eaton.84-e19March 1984
A Summary of Priority Pollutant Data for Point Sources and Sediment in Inner Commencement Bay: A Preliminary Assessment of Data and Considerations for Future Work.84-e23February 1984
Organics in April 17, 1984, Sample from South Lincoln Avenue Ditch Mouth. Memo to Rick Pierce.84-e181984
Photos and appendices for: Completion Report on WQIS Project 5 (Part 1) for the Commencement Bay Nearshore/Tideflats Remedial Investigation: Priority Pollutants and Other Contaminants in City Waterway Storm Drains September-November 1983.84-e21photo-app1984
Sonoco, Sumner - Discharge Affect on Fecal Coliform Levels in White and Puyallup Rivers. Memo to Richard Burkhalter.83-e36December 1983
A Summary of Priority Pollutant Data for Point Sources and Sediment in Inner Commencement Bay: A Preliminary Assessment of Data and Consideration for Future Work Part 6. Summary.83-e24December 1983
Data on Leachate from the B&L Woodwaste Landfill. Memo to Greg Cloud.83-e31November 1983
Comparison of Contaminants in Sediment from the Port of Tacoma Proposed Dredging Project in Blair Waterway with Sediment at the Commencement Bay Deep Water Disposal Site. Memo to Jim Krull.83-e16July 1983
A Summary of Priority Pollutant Data for Point Sources and Sediment in Inner Commencement Bay: A Preliminary Assessment of Data and considerations for Future Work Part 3. Blair Waterway.83-e20July 1983
A Summary of Priority Pollutant Data for Point Sources and Sediment in Inner Commencement Bay: A Preliminary Assessment of Data and Considerations for Future Work Part 2. City Waterway.83-e19May 1983
Buckley STP Parshall Flume and Flow Measurement Survey. Memo to Ken Mauermann.83-e06April 1983
A Summary of Priority Pollutant Data for Point Sources and Sediment in Inner Commencement Bay: A Preliminary Assessment of Data and Considerations for Future Work Part 1. Hylebos Waterway.83-e22April 1983
A Summary of Priority Pollutant Data for Point Sources and Sediment in Inner Commencement Bay: A Preliminary Assessment of Data and Considerations for Future Work Part 5. Milwaukee, Puyallup, St. Paul, Middle Waterways and SW Shore Commencement Bay.83-e231983
Sound Refining Company Class II Inspection, June 30 - July 1, 1981. Memo to Fred Fenske.83-e321983
Reconnaissance and Sampling Survey: Sumner STP and Nabisco Brands November 18, 1982. Memo to Frank Monahan/Ken Mauermann.82-e33December 1982
Receiving Environment Surveys in the Puyallup River at the Tacoma Central (#1) Sewage Treatment Plant, Tacoma, Washington, July 29, 1981, August 25-26, 1981, and February 16-17, 1982. Memo to Frank Monahan.82-e18December 1982
Tacoma Central (#1) Sewage Treatment Plant Class II (Priority Pollutants) Surveys: August 25-26, 1981, and February 16-17, 1982.82-e32October 1982
U.S. Oil and Refining Company Receiving Water Survey, May 5, 1981. Memo to Fred Fenske.82-e02July 1982
Receiving Environment Survey at the St. Regis Paper Company, Tacoma, Washington, August 11-12, 1981. Memo to Fred Fenske.82-e17June 1982
Phenolics in Sitcum Waterway, Tacoma. Memo to Jim Krull.82-e15June 1982
St. Regis Paper Company Class II (Priority Pollutants) Survey, August 11-12, 1981. Memo to Fred Fenske.82-e31June 1982
Receiving Environment Survey in Hylebos Waterway at the Sound Refining Facility, Tacoma, Washington, June 30, 1981. Memo to Fred Fenske through Dick Cunningham.82-e21April 1982
Increasing Interest in Pentachloropropene. Memo to Jim Krull.82-e29April 1982
Receiving Environment Surveys in the Hylebos Waterway at the Penwalt Corporation Facility, Tacoma, Washington, June 2, 1981. Memo to Frank Monahan.82-e19March 1982
Assessment of Surface Water Quality in the Vicinity of Reichhold Chemicals, Inc., Tacoma. Memo to Frank Monahan.82-e03March 1982
Results from Priority Pollutant Analyses of Hooker Intertidal Sediment and Drainage Water below Jones Chemical. Memo to Jim Krull.82-e161982
Pennwalt Corporation Class II Survey, June 2-3, 1981. Memo to Frank Monahan.82-e301982
ASARCO Class II Survey - February 24-25, 1981. Memo to Rick Pierce.81-e14December 1981
U.S. Oil and Refining Company Class II Inspection, May 5-6 198181-e32October 1981
Reichhold Chemicals, Inc., Class II Inspection: 4/21/81. Memo to Frank Monahan.81-e31September 1981
Jones Chemical, Tacoma. Memo to Darrel Anderson.81-e30May 1981
Hooker Chemical Corp., Tacoma, Class II Inspection.80-e21June 1980
Puyallup River Basin Instream Resources Protection Program80-11-001March 1980
Puyallup White River Basin Instream Resources Protection Program80-IRPP-10March 1980
Enumclaw Sewage Treatment Plant Class II Inspection. Memo to Dave Nunnallee.79-e14October 1979
Pennwalt Corporation, Tacoma, Class II Inspection.79-e18September 1979
Hylebos Waterway Water Quality Survey, June 11, 1979. Memo to Jim Oberlander.79-e01August 1979
Follow-up Survey on Boise Creek (after removal of Enumclaw STP discharge). Memo to Dave Nunnallee.79-e10July 1979
ASARCO Class II Survey. Memo to Rick Pierce.79-e08April 1979
Crown Zellerbach Pulp Mill Class II Inspection. Memo to Fred Fleske.78-e09June 1978
Weyerhaeuser Sawmill Class II Inspection. Memo to Ron Devitt.78-e25May 1978
Standard Brands Class II. Memo to Frank Monahan.78-e35May 1978
The Impact of Enumclaw Trickling Filter Effluent on Boise Creek (March 21, 22, 1978.) Memo to Ron Devitt.78-e32April 1978
Enumclaw STP Class II Inspection. Memo to Ron Devitt.78-e24April 1978
Flow Measurement at Crystal Mountain STP, Pierce County. Memo to Jim Oberlander.78-e261978
Sumner STP Class II Inspection. Memo to Ron Robinson.78-e361978
Puyallup STP Class II Inspection. Memo to Ron Robinson May 4, 1977.77-e15May 1977
Ground-Water Conditions in the Area of Swan Creek, Pierce CountyOFTR 77-08March 1977
Puyallup STP Class II Inspection. Memo to Ron Robinson May 13, 1976.76-e12May 1976
Cherrywood Mobile Manor STP Class Inspection. Memo to Ron Robinson.76-e06May 1976
North End Sewage Treatment Plant (Tacoma) Class II Survey. Memo to Ron Pine.75-e23December 1975
Survey at St. Regis Paper in Tacoma. Memo to Mike Knudson.74-e59June 1974
Survey at Kaiser Aluminum in Tacoma. Memo to Mike Knudson.74-e43June 1974
Tacoma Narrows STP Efficiency Study. Memo to Mike Price and Ron Robinson.74-e12March 1974
Compliance Monitoring of the Fibreboard Corporation at Sumner. Memo to Jim Knudson.74-e60February 1974
Comments on Report "Subtidal Sludge Deposit Survey." Memo to Jim Knudson.74-e801974
Ruston STP Efficiency Study. Memo to Mike Pierce.73-e75October 1973
Efficiency Study at Tacoma General STP #1. Memo to Mike Price.73-e76October 1973
Cherrybrook Mobil Home STP. Memo to Ron Robinson, Mike Price, Ron Devitt, and Ron Pine.73-e06October 1973
A.I.W. Survey, Weyerhaeuser Company - White River Operations near Enumclaw. B. Water Quality of Boise Creek. Memo to Bill Burwell.72-e14September 1973
Puyallup Sewage Treatment Plant. Memo to Ron Robinson.73-e20September 1973
Orting Sewage Lagoon Study. Memo to Ron Robinson and Mike Price.73-e21August 1973
Carbonado STP Survey. Memo to Mike Price.73-e60February 1973
Wilkeson STP Efficiency Study. Memo to Mike Price.73-e64February 1973
Rainier State School, STP Efficiency Study. Memo to Mike Price.72-e13December 1972
St. Regis, Tacoma - Clarifier Efficiency. Memo to Jim Knudson.72-e10September 1972
Boise Creek Survey. Memo to S.A. Messman.72-e11August 1972
Enumclaw STP. Memo to Stew Messman.72-e12July 1972
Monitor on Puyallup River. Memo to Gene Asselstine.72-e001972
Boise Creek Survey. Memo to S.A. Messman.71-e04December 1971