Permit Register - October 25, 2003 - Volume 4 Number 25


Department of Ecology, Industrial Section

Site Name Alcoa Primary Metals Intalco Works (INTALCO)
Site Address 4050 Mountain View Road, Ferndale, WA 98248
Mailing Address Same 
Permit Action DP - Issuance of a draft permit/renewal
Description of Facility Intalco --a primary aluminum smelter-- extracts metal (alumina) from ore through an electro-chemical process that produces particulate matter and gaseous fluoride emissions.
Annual Actual Emissions

Calendar Year 2001

Total Particulate:167 tons per year (tpy)
CO: 5343 tpy
NOx:30 tpy
SO2:674 tpy
PM10:167 tpy
VOCs:23 tpy
Additional Comments Not Applicable
Comment Period October 29 - December 2, 2003
Modification:
Date Determination  
Public Hearing TBD
Agency Contact Person Dolores Mitchell

Southwest Clean Air Agency

Site Name TransAlta Centralia Generation, LLC 
Site Address 913 Big Hanaford Road, Centralia, WA 98661
Mailing Address Same 
Permit Action SI - Realted activities that the permitting authority considers to involve substantial public interest 
Description of Facility Power Plant 
Annual Actual Emissions

Calendar Year 2002

Total Particulate:2226  tons per year (tpy)
CO:1535  tpy
NOx:15528  tpy
SO2:19034  tpy
PM10:1444  tpy
VOCs:182  tpy
Additional Comments Not Applicable
Comment Period Order of Approval 01-2350R2 was issued final on October 15, 2003
Modification: Order of Approval 01-2350R2 approves installation and operation of a 20.9 MMBtu/hr natural gas fired auxiliary boiler and modifies various existing permit terms 
Date Determination  
Agency Contact Person Clint Lamoreaux 360-574-3058 ext. 31 clint@swcleanair.org 

Agencies not listed have no permit actions to report at this time.