Boeing Renton 08-01 10-07-08 Final
Agrium USA Kennewick 04-01 07-11-08 Final 1st Amendment

Conoco Phillips

Ferndale 00-02    Amd. 5 8/23/08 Final Permit
Agrium US Inc Kennewick 04-01 7/11/08 Final Permit
Nucor Steel Seattle 07-02 2/15/07 Final Permit
BP Blaine 07-01 11/19/07 Final Permit
Cardinal FG Winlock 03-03 2/14/08 Final Permit
Boeing Everett 06-04 7/27/07

Final Permit

Guardian Fiberglass Moses Lake 06-03 7/11/07

Final Permit

Simpson/Kraft Tacoma 06-02 05/22/07 Final Permit
Grays Harbor Paper Hoquiam 06-01 11/17/06

Final Permit

Longview Fiber Longview 01-03 09/18/06 Final 2nd Amendment
NW Pipe Line Sumas 01-08 06/14/06 Final 3rd Amendment
NW Pipe Line Mt Vernon 01-09 06/14/06 Final 5th Amendment
Boise Cascade Wallula 01-07 02/01/06 Final 1st Amendment
Boeing Everett 05-02 10/10/05 Final Permit
Conoco Phillips Ferndale 05-01 10/31/05 Final Permit
Sierra Pacific Skagit Co. 05-04

12/14/05

Final Permit
Waste Treatment Hanford 02-01 10/02/05 Final 2nd Amendment

Conoco/ Phillips

Ferndale 00-02

06/15/05

Amendment 3

Boeing Everett 91-06

Amd 2

06/10/05

Approval of Rescission
91-03/05 Amendment
91-06 Approval

BP Isomerization Project Blaine 02-04

Amd 1

4/20/05 Amendment 1
Boeing Everett 91-06 06/13/05 Final
Boeing Everett 91-03/05 06/13/05 Final/Rescission
Darrington Cogeneration Facility Darrington 03-04 01/18/05 Final
Northwest Pipeline Corporation Mount Vernon Compressor Station

01-09

07/15/04

Final 4th Amend.
Northwest Pipeline Corporation Sumas Compressor Station 01-08 07/15/04 Final 2nd Amend.
Cardinal FG Company Winlock

03-03

10/6/04

Final

Agrium US Inc. Kennewick

04-01

08/27/04

Final
Weyerhaeuser Norpac Seattle 97-01 04/24/04 Amend. 2
Waste Treatment Plant Hanford 02-01 11/12/03 Final, Amend. 1

TransAlta Centralia Generation LLC 

Centralia

01-01 Amd 1

01/30/03

Final Approval

Puget Sound Energy Fredonia Station 01-04 07/18/03 Final Approval
Boise Cascade Corp. Kettle Falls, WA X-08-01 02/14/03 Construction Amendment
Goldendale Aluminum Company Goldendale X-88-01 11/14/03 Amend. 2
BP, Cherry Point Refinery Blaine, WA  02-04 05/15/03 Final Approval
Sierra Pacific Aberdeen 02-02 10/17/02 Final Approval
Northwest Pipeline  Sumas, WA 01-08 10/24/02 Final Approval

Hanford Vitrification Plant

Richland

02-01

11/07/02

Final Approval

NW Pipe Line

Mt. Vernon

01-09

07/24/02

Final Approval (amendment)

PG&E Gas Transmission NW

Rosalia

01-05

05/03/02

Final Approval

Boise Cascade

Wallula

01-07

06/20/02

Final Approval

PG&E Gas Transmission NW

Wallula

01-06

06/26/02

Final Approval

Ash Grove Cement West, Inc.

Seattle

90-3

Amd 3

09/06/01

Final Permit

Longview Fiber

Longview

01-03

12/10/01

Final Approval

Tosco Refining Co.

Bellingham

00-02

04/04/01

FCCU

Port Townsend Paper

Port Townsend

 96-01A

05/20/98

Power Boiler

Boise Cascade Yakima

Yakima

96-03

11/14/96

Final Permit

General Chemical Company

March Point

94-01

08/94

 

Weyerhaeuser Paper Company

Longview

92-03 Amd 1

06/17/93 (Preliminary)

 

Weyerhaeuser Paper Company

Longview

92-03 Amd 1

06/17/93 (Preliminary)

 

Weyerhaeuser Paper Company

Longview

92-03

02/10/93

Final NOC Amendment 4

Weyerhaeuser Paper Company

Longview

92-03

02/02/93 (Final)

 

Northwest Pipeline

Mt. Vernon

93-01

07/14/93

 

Columbia Power

Near Goldendale

92-01

03/27/92 (Final)

Power Plant

Northwest Pipeline Company

Sumas

92-04

08/08/92 (Final)

Compressor Station

Boeing Airplane

Everett

92-05

11/06/92 (Final)

Manufacturing Plant

Pacific Gas Transmission

Starbuck

92-02

06/16/92 (Final)

Compressor Station 7

Weyerhaeuser Paper Company

Longview

92-03

09/01/92 (Preliminary)

 

Boeing Airplane

Everett

91-01A

10/08/92

Paint Hanger, Building 45-04, Modification

Tenaska Washington, Inc.

Ferndale

91-04

05/29/92 (Final)

Amendment 1

Boeing Airplane

Everett

91-06

01/03/92

 

James River Corporation

Camas

88-3 (Mod)

10/17/91

Energy recovery and mill modernization projects

Enserch Development Corp.

Bellingham

91-02

09/26/91


Amendment 2

Boeing Airplane

Everett

91-03

07/10/91

New Paint Building 40-37

Tenaska Washington, Inc.

Ferndale

91-04

12/31/91 (In progress)

Cogeneration Facility

Boeing Airplane

Everett

91-01

05/06/91

Paint Hanger, Building 45-04

Amendment 2

Boeing Airplane

Everett

91-05

12/28/91

New Corrosion Inhibitor Compound, Buildings 40-25 & 40-26

Boeing Airplane

Everett

91-06

12/30/91

Tool Positions, Buildings 40-04, 40-25, 40-26, and 40-34

Pacific Gas Transmission Co.

Rosalia

90-2

03/30/90

Compressor State 6-Modification

Spokane Regional Waste to Energy Project

Spokane

88-1B

09/01/89

Revised Final Approval

James River Corporation

Camas

88-3

14-Feb-89

Energy and Recovery Modernization Project

Boeing Airplane

Renton

88-4

01/30/89

Paint Hanger

Arco Petroleum Products Co.

Ferndale

89-2

01/30/89

Revised NO2 Limit

Boeing Airplane

Auburn

88-05

04/25/89

Sheet Metal Center

Spokane Regional Waste to Energy Project

Spokane

88-1

04/20/88

Spokane Regional Waste to Energy Project

Chevron Chemical Co,. Inc.

Kennewick

88-2

08/03/88

Fertilizer Plant

Energy Products of Idaho

Tacoma Tideflats

6

04/08/86

Cogeneration Project

Arco Petroleum Prod. Co.

Cherry Point

7

03/13/86

Gasoline Reformer

Pacific Gas Transmission Co.

Wallula

8

09/09/86

Compressor Turbine Replacement

PPG Industries, Inc.

Chehalis

4

06/21/85

Float Glass Plant

Arco Petroleum Prod. Co.

Cherry Point

5

12/17/85

North Vacuum Heater Modification

Port Townsend Paper Cp.

Port Townsend

1

06/01/84

Modernization of Kraft Pulp and Paper Mill

Intalco Aluminum Co.

Ferndale

2

10/17/84

Dry Scrubber on Anode Bake Facility

Arco Petroleum Prod. Co.

Cherry Point

3

12/20/84

Third Coke Calciner

Puget Sound Naval Shipyard

Bremerton

X83-05

05/12/83

 

Washington Water Power

Creston

X83-01

11/18/82

Completemess date question: 1/8/82 or 6/1/81; Project was cancelled.

Puget Sound Power and Light

Mount Vernon

X82-09

08/24/82

Fredonia Station

Alumimun Company of America

Wenatchee

X82-04

02/13/82

 

Tacoma City Light

Tacoma

X82-06

05/12/82

 

Longview Fibre Company

Longview

X81-10

04/28/81

 

Washington Water Power

Kettle Falls

X80-11

07/29/80

 

Fairchild Air Force Base

Fairchild AFB

X80-12

07/29/80

 

Puget Sound Power and Light

Fredrickson

X80-17

09/26/80

Combustion turbine

Kaiser Tacoma

Tacoma

X80-13

07/19/80

 

Department of Energy

Hanford

X80-14

10/01/80

 

Boise Cascade Lumber

Kettle Falls

X79-07

07/20/79

 

Murphy Brothers, Inc.

Spokane

X79-03-M

04/28/79

This project was never constructed; went through modified PSD process

Guy Bennett Lumber

Wilma

X79-11

09/12/79

Became exempt when PSD regulations were changed 8/7/81

Vaagen Brothers Lumber (Louisiana Pacific)

Ione

X79-12

08/17/79

Went through modified PSD process

Vaagen Brothers Lumber (San Poil Lumber)

Republic

X79-13

08/08/79

Went through modified PSD process

U.S. Oil & Refining Company

Tacoma

X79-9

08/06/79

 

Boise Cascade Plywood

Kettle Falls

X80-01

12/19/79

Final Approval

Puget Sound Power and Light

Point Whitehorn

X80-02

12/20/79

 

Boise Cascade

Wallula

X77-04

03/31/78

 

Columbia Aluminum (Martin Marietta)

Goldendale

X78-02

08/31/78

 

Daishowa America Port Angeles 90-01 Withdrawn Final permit not issued, applicant withdrew project

Kaiser Tacoma

Tacoma

X83-06

Cancelled

Kaiser cancelled this project

Washington State University

Pullman

Not Issued

Not Issued

Exempted from PSD by request of the governor (Educational Institution)