Listed below are Coastal Zone Consistency determinations for projects in Ecology's Southwest Region that are not associated with a 401 Water Quality Certification.
The determinations are sorted by the date of issue.
To view a Coastal Zone Consistency determination, click on the Applicant Name in the table below. (pdf)
|
Issue Date |
Docket # | Applicant | Project Description | County |
| April 8, 2008 | 5397 | Corps of Engineers | Julia Butler Hansen Columbian White-tailed Deer National Wildlife Refuge Section 536 Habitat Restoration Project | Wahkiakum |
| March 28, 2008 | 3817 | Aho Construction I, Inc. | Amends the Wetland Mitigation Information for the construction of Damaari Terrace Residential Development within the City of Vancouver. | Clark |
| February 21, 2008 | 5409 | Pioneer Estates | Place fill in Prior Converted Cropland Wetlands for construction of a cul-de-sac and S 10th Street off of the proposed Union Ridge Parkway to access future developments within Union Ridge | Clark |
| March 20, 2008 | 5448 | Clark County Public Works | Place fill in 0.08 of an acre of isolated wetland for improvements to NE 88th Street | Clark |
| February 29, 2008 | 5436 | Park Junction LLC | Master Planned Resort Development | Pierce |
| February 19, 2008 | 5400 | WA State Dept of Transportation | Humptulips Bridge Scour Repair project | Grays Harbor |
| February 15, 2008 | 5316 | Wahkiakum Dept of Public Works | Placement of up to 265,373 cu yds of dredged material along 3.300 ft of shoreline on Puget Island | Wahkiakum |
| February 15, 2008 | 5333 | Port of Camas/Washougal | Maintenance dredging of the Port of Camas/Washougal marina | Clark |
| February 14, 2008 | 5360 | Finavera Renewables, Ltd. | 1.0 megawatt wave energy demonstration power plant in Makah Bay | Clallam |
SWRO 2007 Decisions : SWRO 2006 Decisions : SWRO 2005 Decisions : SWRO 2004 Decisions
Copyright © Washington State Department of Ecology. See http://www.ecy.wa.gov/copyright.html.