Permit time extensions
The permit time clock starts after all needed permits and approvals are
received from all agencies.
A permit's timeframe is usually 5 years but may be longer.
Construction must commence within 2 years; a single 1-year extension may
be granted.
Permitted development must be completed within 5-year (or other) permit
timeframe; a single 1-year extension may be granted.
Local governments may revise a permit after its expiration
under limited
conditions.
For more information
Rule:
WAC 173-27-090
For specific information about a city or county
permit process, visit the
Local Planning Page and click on the
map, or contact a shoreline specialist at the appropriate
Ecology regional office.
|