Oil transfer requirements refer to the procedures and equipment standards necessary for safe oil transfers.
| Requirements include: | |||||
|
|
Pre-booming |
|
Oil transfer equipment |
|
Oil transfer operations |
|
|
Equivalent compliance |
|
Safe vessel access |
|
Emergency shutdown |
|
|
Alternative measures |
|
Communications |
|
Pre-transfer conference |
|
|
Advance notice of transfer |
|
Preload or cargo transfer plan |
|
Adverse weather and sea conditions during transfer |
|
|
New! Safe and Effective Threshold Values | ||||
| Note: Oil Transfer Rules Compliance Schedule | |||||
| Alternative Measures Requirements | ||
| Q: What are Alternative Measures? | ||
| A: For Rate A transfers: Alternatives Measures are actions which a class 1 facility must take when it is not safe and effective to pre-boom. For Rate B transfers, they are actions to be taken when the facility elects not to pre-boom. The alternative measures to be taken for a Rate A transfer differ from those for a Rate B transfer. | ||
| Q: When must Alternative Measures be in place at oil transfer locations? | ||
| A: Unless pre-boomed, or operating under an approved “Equivalent Compliance Plan,” Class 1 facilities conducting Rate A or Rate B transfers must have alternative measures in place by February 25, 2007. | ||
| Rate A Requirements | ||
| Q: What specifically is required to implement the alternative measures during a Rate A transfer? | ||
A: For
rate A transfers, a delivering class 1 facility must:
|
||
| Rate B Requirements | ||
| Q: What specifically is required to implement the alternative measures during a Rate B transfer? | ||
A: For
Rate B transfers, a delivering class 1 facility must:
|
||
| back to top | ||
| Equivalent Compliance Measures | ||
| Q: Can a Class 1 facility propose innovative or special measures to be taken in place of the “alternative measures” required? | ||
| A: Yes. An “Equivalent Compliance Plan” may be submitted 120 prior to planned use of the proposed equivalent measures. The plan must be reviewed and approved by Ecology before it can be used as a substitute for the alternative measures. To be approved, the Equivalent Compliance Plan should be site-specific and must provide protection that is equivalent or better than the alternative measures. | ||
| Q: Can an approved Equivalent Compliance Plan substitute for the pre-booming requirements in the oil transfer rule? | ||
| A: No. Rate A transfers at a Class 1 facility must be pre-boomed if it is safe and effective to do so. An approved Equivalent Compliance Plan does not relieve the facility from the rule requirement to pre-boom but can substitute for the appropriate Rate A or Rate B alternative measures. | ||
| back to top | ||