Operations Manual Tracking Sheet for Class 1 Facilities

This list will be updated on a frequent basis to track operations plan as they are being reviewed by Ecology.

Last updated 6/30/2009

COMPANY NAME PLAN RECEIVED CONFIRMATION LETTER SENT CONDITIONAL APPROVAL DEFICIENCY DUE FINAL APPROVAL
BP Cherry Point Refinery February 22, 2007 February 28, 2007 October 12, 2007 February 26, 2009  
BP West Coast Products-Harbor Island Terminal February 28, 2007 February 28, 2007 October 12, 2007 February 26, 2009 February 26, 2009
Chevron Pasco Facility June 21, 2007 June 21, 2007 July 26, 2007 August 27, 2007 March 20, 2008
Conoco Phillips Ferndale Refinery February 22, 2007 February 28, 2007 October 12, 2007 February 26, 2009 February 26, 2009
Conoco Phillips Renton Terminal May 14, 2007 May 14, 2007 July 17, 2007 August 19, 2007 June 22, 2009
Conoco Phillips Tacoma Terminal February 26, 2007 February 28, 2007 October 12, 2007 February 26, 2009 February 26, 2009
Conoco Phillips Yellowstone Pipeline February 26, 2007 February 28, 2007

 

April 26, 2007 April 30, 2007
Imperium Renewables Grays Harbor December 4, 2007 December 4, 2007 December 11, 2007 February 26, 2009  
Kinder Morgan-Harbor Island Terminal March 22, 2007 March 23, 2007 October 12, 2007 February 26, 2009 February 26, 2009
McNeil Island Correctional Facility April 6, 2007 April 6, 2007 July 20, 2007 August 20, 2007 May 2, 2008
Naval Air Station Whidbey Island February 23, 2007 February 28, 2007 October 12, 2007 February 26, 2009 February 26, 2009
Navy Manchester Fuel Depot February 28, 2007 February 28, 2007 May 17, 2007 February 26, 2009 February 26, 2009
NuStar Tacoma February 20, 2007 February 28, 2007 October 12, 2007 February 26, 2009 February 26, 2009
NuStar Vancouver February 25, 2007 February 25, 2006 October 12, 2007 February 26, 2009 June 23, 2009
Paramount Richmond Beach Terminal February 16, 2007 February 28, 2007 October 1, 2007 February 26, 2009 February 26, 2009
Port Townsend Paper Mill March 29, 2007 March 29, 2007 August 30, 2007 September 29, 2007  
Rainier Petroleum-Seattle February 26, 2007 February 28, 2007 October 12, 2007 February 26, 2009  
Shell Anacortes Refinery February 28, 2007 February 28, 2007 October 12, 2007 February 26, 2009 February 26, 2009
Shell Seattle February 27, 2007 February 28, 2007 October 12, 2007 February 26, 2009 February 26, 2009
Sound Refining-Tacoma March 15, 2007 March 15, 2007 October 12, 2007 February 26, 2009 February 26, 2009
Tesoro Anacortes Refinery March 21, 2007 March 22, 2007 October 12, 2007 February 26, 2009 February 26, 2009
Tesoro Port Angeles Terminal March 21, 2007 March 22, 2007 July 17, 2007 February 26, 2009 February 26, 2009
Tesoro Vancouver Terminal March 20, 2007 March 22, 2007 July 25, 2007 February 26, 2009 February 26, 2009
Tidewater, Snake River Terminal March 7, 2007 March 8, 2007 October 22, 2007 February 26, 2009 February 26, 2009
Tidewater, Wilma Terminal March 7, 2007 March 8, 2007 October 18, 2007 February 26, 2009 February 26, 2009
US Oil Refinery February 26, 2007 February 28, 2007 May 29, 2007 February 26, 2009 February 26, 2009
Weyerhaeuser Longview Pulp Mill March 20, 2007 March 20, 2007 October 22, 2007 February 26, 2009