 |
|

The Columbia River at the former site of the Davy
Crockett. The vessel was fully removed from the river on August 25 and the work
site cofferdam was fully removed by November 17, 2011.

View of the Davy Crockett barge in January 2011.
Davy Crockett
Project Timeline (last updated 1/10/12)
Photo Gallery - (Last Updated
11/30/2011)
12/10/11 USCG Davy Crockett Mission
Profile Video
SEATTLE - Authorities
respond to the illegal scrap metal salvage of the flat-deck Barge Davy Crockett
on the Columbia River near Camas, Wash., on Jan. 27, 2011. This comprehensive
summary depicts the efforts of the more than nine month response. U.S. Coast
Guard video by Petty Officer 2nd Class Eric J. Chandler.
PAST INCIDENT REPORTS
(PDF Format available).
INCIDENT BACKGROUND
The Washington Department Ecology received reports of oil sheen on the Columbia
River near Vancouver, Wash., Jan. 27, 2011, and traced it 11 miles upstream to
the 431-foot flat-deck barge Davy Crockett. Reports of sheen were reported as
far as 14 miles downstream.
The vessel was partially sunk near the north shore between Vancouver and Camas,
Wash., four miles upstream of the I-205 Bridge. The Davy Crockett had begun
leaking oil due to improper and unpermitted salvage operations.
Response efforts began immediately to contain oil and stabilize the vessel. The
Coast Guard, Washington Department of Ecology and Oregon Department of
Environmental Quality are jointly managing the response and salvage effort using
the National Incident Management System.
In
mid-February Coast Guard Commandant Adm. Robert Papp authorized Coast Guard
Sector Columbia River to remove and destroy the barge Davy Crockett. In his
authorization memo, Adm. Papp stated that “destruction of this vessel is
appropriate to mitigate the threat of continued discharge of oil, oil water
mixtures and hazardous substances into the waterway.”
DAVY CROCKETT HISTORY
The Davy
Crockett is a former Navy Liberty Ship that was converted to a flat deck barge.
As with many aging vessels, ownership has changed several times over the years.
The most recent ownership change is believed to have occurred in mid-2010. The
vessel is located on Washington state-owned aquatic lands.
|
|
SUMMARY INFORMATION
Date of Incident:
Response began
January 27, 2011
Project Completed:
November 17, 2011
Location:
North bank of the Columbia River near Camas, Washington
Product/Quantity:
Lube, bunker and diesel oil.
Cause:
Damaged derelict vessel.
Funding for response:
Federal Oil Spill Liability Trust Fund
MEDIA CONTACTS
Department of Ecology
Ron Holcomb
Office: 360-407-6373
Cell: 360-951-1669
U.S. Coast Guard
Petty Officer Shawn Eggert
Cell: 206-819-9154
Shawn.D.Eggert@uscg.mil
RELATED LINKS
USCG Media Port -
District 13 Public Affairs
INTERVIEWS
Interview with Washington State On Scene Coordinator
NEWS RELEASE
USCG Press Release
-
December 19, 2011
Joint Press Release -
November 23, 2011
Dept. of Justice News Release - Sept. 29, 2011
Photo News Release-
August 25, 2011
Joint Press Release - August 25, 2011
Joint Media Packet - May 6, 2011
USCG Press Release -
April 19, 2011
USCG Press
Release - March 30, 2011
USCG Press
Release - March 11, 2011
USCG Press
Release - March 10, 2011
USCG Press Release - February 17, 2011
USCG Press Release - February 4, 2011
Joint Press Release - February 3, 2011
Joint Press Release - February 1, 2011
Joint Press Release - January 31, 2011
Joint Press Release - January 30, 2011 #2
Joint Press Release - January 30, 2011
Joint Press Release - January 30, 2011 #1
USCG Press Release - Jan. 21,
2011
SOCIAL MEDIA
|
NEWS UPDATE - November 23, 2011
On Nov. 17, 2011, workers removed the final piece of the sheet pile cofferdam from the barge Davy Crockett work site. This signals the end of a 10-month effort to prevent a catastrophic release of 38,000 gallons of heavy oil and other hazardous materials from the former Liberty ship. See the Nov. 23, 2011 news release for more information.
The last section of the barge itself was lifted from the Columbia River on Aug. 25, 2011. See the project photo gallery for a visual timeline of the entire project.
Last updated
11/23/2011
|
Incident duration |
295
days |
|
Vessel removed (8/25/11) |
211 days |
|
Cofferdam removed (11/17/11) |
295 days |
|
|
|
|
Injuries |
0 |
|
Sediment Collected |
85.5 cubic yards |
|
|
|
|
Total Oil water mixture recovered to date |
1.6
million
gallons* |
|
Total steel removed |
3.56 million pounds** |
|
Debris
& oiled debris removed |
1.25 million
pounds |
|
Bunker oil recovered |
38,397 gallons |
|
Asbestos removed |
4,850
pounds |
|
|
|
|
Samples analyzed to date (e.g. water, oil sediment) |
227 |
|
Obligated costs to date |
$22 million |
|
|
|
**This is the weight of the steel
after it was cleaned and recycled. Prior figures reported were for
uncleaned steel, which reflected a heavier total.
*This figure represents the amount of
oily water mixture that has been recovered directly from the barge
Davy Crockett during response operations. An initial unrecovered
release of an estimated 70 gallons of oil was documented on January
27, 2011 the day the vessel was discovered to be leaking oil. |
ENVIRONMENTAL PROTECTION
All activities involving the destruction
and removal of the Davy Crockett were designed to minimize environmental
impacts. The impermeable oil and silt barrier inside the metal cofferdam
along with sorbent oil collection booms prevented tar balls and oil sheen
from discharging into the Columbia River downstream of the work site. Oil
containment boom was deployed outside the cofferdam as a preventative
measure in case there is a release of oil from the work site. Additional
on-water oil recovery resources and oil containment boom were staged nearby
as further protection.
Oil, oily water and contaminated water from
the vessel’s holds and tanks were collected throughout the cleanup
effort and taken off-site for proper disposal. In addition, wash water from
cleaning operations and stormwater collected on the Davy Crockett and work
barges was put through an on-site water filtration system and then disposed
of through the city of Portland’s wastewater treatment system.
Water quality samples upstream, downstream
and inside the cofferdam were being collected on a periodic basis in order to
evaluate the effectiveness of work activities to minimize water pollution.
Sediment samples around the Davy Crockett
and inside the cofferdam were also collected periodically during the
project. After the vessel was removed from the river, deconstruction debris,
contaminated sediments, metal slag and scale (metal “flakes”) were removed
by divers using hand-operated dredging equipment. A final set of sediment
samples were collected at the conclusion of the 38-day dredging operation.
|
|
|