
SS CATALA HOMECLEANUP PLANS: |
||
Cleanup Progress Report - August 2006Update information: Contractors have completed the sheet pile wall around three sides of the Catala. This greatly enhances the ability to contain any oil that might escape from tanks remaining in the ship. Related Information: A Community Meeting held in Ocean Shores during the evening of August 24th was well attend by interested and concerns local citizens. At this meeting, Ecology announced that the project may not be completed by the end of September due to additional work to completely surround the ship with sheet pile, and difficulty in rapidly removing sand, steel and water from the deeply buried stern tanks. If necessary, the sheet pile can be left over winter and the removalproject restarted next year. This would be timed to minimize disturbance to migratory and nesting birds. DNR also announced their intention to secure funding to have the Catala hull completely removed from Damon Point. Amount of oil recovered: As of August 25th, 31,000 gallons of oil and oily water have been removed from two of the five tanks on board the Catala. Week 1: July 31 - August 3Click images below to see enlargements
Global Diving and Salvage, hired by the state, has cleared the laydown area of drift logs and is preparing the Catala site for equipment. (Aug 3, 2006) Contractor National Response Corporation has deployed hard boom around the Catala and into channel to protect the lagoon. (Aug 3, 2006) The crane is set up for driving sheet pile & pile placement is scheduled to start soon. Global Diving and Salvage has cleared vegetation and logs from top of the Catala. (Aug 3, 2006) Week 2: August 8 - 11On August 9, sand erosion exposed a hole in the side of the shipwreck. The cleanup contractor suspended the sheet pile driving work for a couple of days after observing an oil sheen escaping into water inside the sheet pile. The contractor brouth in vacuum trucks and crews to pump as much oil and water as possible prom two tanks, including the one with the newly revealed hole. The plan is to draw the oil levels down to a point where oil cannot easily escape and patch any new holes that are discovered. As of about 3:30 p.m. August 9, contractors had pumped out 1,700 gallons of oily water fromt he Catala and the pumping continued. Click images below to see enlargements
(Aug 08, 2006) A large crane is used to place the steel wall around the Catala. The craine picks up individual pieces of 40 foot long sheet steel. The all segments are driven vertically into the sand. (Aug 08, 2006) Week 3: August 21 - 25Click images below to see enlargements
(Aug 19, 2006) (Aug 19, 2006) |
||
Copyright © Washington State Department of Ecology. See http://www.ecy.wa.gov/copyright.html.