
SS CATALA HOMECLEANUP PLANS: |
||
Cleanup Progress Report - January 2007Season 1 Completed: Efforts to remove heavy fuel oil from the SS Catala were called off for the season on October 20, 2006. The second season of the project will start again around May 1, 2007. Ecology's assessment of the situation? This was a "near miss". Records show that an attempt was made to remove oil in the ship during a 1980 salvage operation. Holes were cut in the side of the ship and the tank tops to pump out some of the oil. These holes were patched before the hull was buried in sand, but the patches were not very secure. Stream erosion along one side of the Catala in 2006 very nearly uncovered a patch on the port side of the vessel. Thousands of gallons of oily water and heavy oil could have been released into Grays Harbor if this patch had been uncovered. During the summer of 2006, the Catala was enclosed with a steel wall, and heavy oil and oil-contaminated water was pumped from four tanks in the hull. Oil-contaminated sand was removed from within the ship. Staff from the Washington Departments of Ecology, Parks and Natural Resources visit the site weekly. Ecology measures the position of the ship, inspects the security fence and makes sure the tanks are full of water. The steel wall and ship remain strong and stable even after the severe storms of November and December 2006. There is only a minimal amount of oil sheen showing up on top of water inside the steel wall. Why fill the tanks with water? Even though the ship is over 80 years old, and has been buried in sand for the last 40 years, it still wants to float. In September, after the sand was removed from the top of the ship and several of the tanks had been emptied, the ship rose as much as 18 inches out of the sand! Filling the tanks with water and allowing water to accumulate on top of the ship adds the weight necessary to keep it stable. Season 1 Accomplishments: The project started on July 27 and operations continued, often around the clock, through October 20, 2006. Significant items at seasons end:
Plan for 2007: While the structure and ship are stable, Damon Point is not. The beach on the south side of the point has eroded 75 to 100 feet. If the erosion continues, it could take out the access road, greatly complicating the plans for Season 2. Assuming the access road is still useable, Season 2 of project work is expected to start in May 2007. This early start is being coordinated with biologists from U.S. Fish and Wildlife Service and the Washington Department of Fish and Wildlife. The goals for next season are to finish removal of oil contaminated sand and any remaining oil in the last tank; remove the ship from the beach; and restore the site back to normal conditions. The season will involve four main phases, including:
Phase 1: Completion of fuel and soils removal from vessel (approxmately five weeks)
Phase 2: Vessel removal (approxmately four weeks) Phase 3: Removal of contaminated soils under hull (if required approxmately two to three weeks) Phase 4: Site restoration / Project completion (approxmately four weeks) Ecology will continue to pay for activities related to removal of oil and hazardous materials. The Washington Department of Natural Resources is seeking funding from the State Legislature to pay removal of the ship. Click images below to see enlargements
View of Damon Point from the parking area. Location of the Catala is noted in the background.
(Jan. 5, 2007) |
||
Copyright © Washington State Department of Ecology. See http://www.ecy.wa.gov/copyright.html.