Port Townsend Paper Company > Additional Information
Port Townsend Paper Corporation Air Operating Permit
UPDATED (June 15, 2010)
We reissued Port Townsend Paper Corporation's (PTPC's) Air Operating Permit (AOP) on April 28, 2010.
The effective date is May 1, 2010.
Click
here to see the final permit and supporting documents.
Consolidated Order No. 2892 05AQ
The conditions of Air Order No. 2892 05AQ are applicable requirements in the permit. The order places
limits and requirements on some PTPC air emissions. We modified it along with the permit to
meet the PCHB's requirements. The introductory portion of the order
lists the modifications to the order.
PTPC AOP Timeline
| April 5, 2006 |
Public comment period opens for Proposed AOP renewal |
| May 31, 2006 |
Ecology holds public workshop followed by a hearing for Proposed AOP renewal held in Port Townsend |
| August 10, 2006 |
Ecology issues Consolidated Order No. 2892 05AQ to PTPC |
| January 17, 2007 |
Ecology renews PTPC's AOP |
| December 21, 2007 |
Appeal filed with the Pollution Control Hearing Board (PCHB) |
| January 18, 2008 |
PCHB remands permit back to Ecology in light of comments
received from the Environmental Protection Agency (EPA) |
| April 24, 2009 |
Public
comment notice published in Ecology's AOP register |
| April 29, 2009 |
Public comment period opens for Proposed AOP and Modified Consolidated Order No. 2892 05AQ |
| June 2, 2009 |
Public meeting and hearing for Proposed AOP and Modified Consolidated Order No. 2892
05AQ held in Port Townsend |
| June 15, 2009 |
Public comment period for Proposed AOP and Modified Consolidated Order No. 2892 05AQ ends |
| February 26 - April 11, 2010 |
EPA 45 day review. |
| April 12 - June 11, 2010 |
EPA petition period |
| April 28, 2010 |
Permit reissued |
| April 28 - May 28, 2010 |
PCHB appeal period |
| May 1, 2010 |
Permit effective date |
Other PTPC Air Quality Activities and Data
| April 8, 2008 |
WA
State Dept of Health (DOH) publishes Summary of Air Quality Issues in Port Townsend -
Jefferson County, Washington |
| July 29, 2008 |
Ecology issues Agreed Order 5771 |
| September 10, 2008 |
Ecology receives PTPC's submission for Agreed
Order 5771 Part B2 - Weather Station |
| October 24, 2008 |
Ecology receives PTPC's submission for Agreed Order 5771 Part B3:
|
| January 23, 2009 |
Ecology receives PTPC's submission for Agreed Order 5771 Part B1 - Report on Hazardous Air Pollutants for
2002, 2005, 2007 |
| March 19, 2009 |
Ecology receives email and data from EPA's Residual Risk Model results at PTPC |
| May 2010 |
PTPC submits a Notice of Construction (NOC)
application for their cogeneration project. |
| July 7, 2010 |
Ecology does not object to PTPC's
Prevention of Significant Deterioration applicability
analysis for the cogeneration project. |
| July 9, 2010 |
Ecology issues original Determination of
Nonsignificance (DNS) for PTPC's cogeneration project. This is withdrawn on
September 23, 2010 and another is reissued to include a formal comment period. |
| July 16 - August 18, 2010 |
Ecology holds a public comment period and hearing on draft NOC order 7850 for
PTPC's cogeneration project. |
| September 24 - October 8, 2010 |
Ecology holds a public comment period on the
reissued DNS and
SEPA checklist for PTPC's cogeneration project. |
| October 22, 2010 |
Ecology issues NOC order 7850 |