APPROVED BY: ________________
PROCEDURE
PRO 310 REQUESTING A CONTRACTOR
ACTION BY: ACTION:
Project/Site Manager 1. Determines whether project is listed
in program plan and has a PIC.
a. If No, THEN, follows
procedure-"Requesting a Program Index Code"
PFM-221.
b. If Yes, THEN, proceed with Step 2,
below.
2. Determines if there are sufficient
contract dollars in the program plan
for the proposed contract.
a. If No, THEN, proceed with Step 3,
below.
b. If Yes, THEN, proceed with Step 15,
Preparing the Contract Request Form.
3. Prepares and Signs Conceptual
Approval Form (CAF) and Workplan
Amendment Forms.
4. Submits CAF and Workplan Amendment
Forms to Section Manager.
Section Manager 5. If approves, signs forms and sends
them to the Budget Planner.
a. If denies request, returns unsigned
forms to Project/Site Manager.
Budget Planner 6. Discusses LUST requests with the
LUST Coordinator and the LUST Contracts
Officer.
7. Reviews the CAF for impact on the
budget and submits to the Program
Manager.
8. Informs Section Manager of any delay
beyond three days after receipt.
Program Manager 9. Approves or denies CAF.
10. Returns signed form to Budget
Planner, or:
11. Returns unsigned form to Section
Manager and informs Budget Planner of
the decision.
Budget Planner 12. Retains original CAF.
13. Distributes copies to:
a. Project/Site Manager
b. Section Manager
c. Fnancial Management Unit Supervisor
d. LUST Coordinator (if LUST site)
14. Modifies Program Plan in Workplan
database.
Project/Site Manager 15. Prepares Contract Request Form
(CRF) for Section Manager's approval.
Section Manager 16. Signs and returns to Project/Site
Manager.
Project/Site Manager 17. Submits CRF, Budget Worksheet and
Scope of Work to Financial Management
Unit Supervisor.
Financial Management 18. Assigns a contractor.
Unit Supervisor
19. Distributes work to Contracts
Officer.
Contracts Officer 20. Contacts Project/Site Manager to
schedule preplanning and scoping
meetings.
21. Requests an addition Conceptual
Approval Form and Workplan Amendment
Form (See Step 2, above) if
contractor's proposal exceeds the
authorized amount by 10% or $25,000.
Return to Top of Page or Procedures List