Spokane River - Upriver Dam PCBs Sediments Site

SITE BACKGROUND

Ecology and Avista Development, Inc. are cleaning up a segment of the Spokane River known as the Upriver Dam PCBs Sediments Site. The site is divided into two projects. Deposit 1 begins directly behind Upriver Dam in the city of Spokane and continues east for approximately 3.6 acres. Deposit 2 is a small 0.25-acre area near Donkey Island in an unincorporated area. Sediments at both project locations are contaminated with Polychlorinated Biphenyls (PCBs). Cleanup is necessary, because PCBs build up in the fatty tissues of humans, fish and animals and may cause harmful health effects.

Benefits of this Project

  • Cleanup improves the health of the Spokane River.
  • These restoration projects reduce contamination in the environment.
  • Reducing contamination provides a safer environment for children, adults, and wildlife who may use these areas.
Fact Sheet: Spokane River Project Update 2007

Fact Sheet Engineering Design Report:
                    English  
                         Русски
                    Español

 Engineering Design Report (English only)      
                    Table of Contents
                    Introduction
                    Deposit 1 Remediation
                    Deposit 2 Remediation
                    Compliance Monitoring and
                        Construction Schedule
                    References
                    Figure 1
                    Figure 2: Deposit 1 Site
                        Overview
                    Figure 3: Deposit 2 Sampling
                    Figure 4: Deposit 1 Site
                        Access Plan
                    Figure 5: Deposit 2 Sampling
                        Station Cores
                    Figure 6: Deposit 2 Access
                        Routes and Staging
                        Stockpiling Areas
                    Figure 7: Timeline for Upriver
                        Dam PCB Sediment Site
                        RD/RA
                    Appendix A: Draft Final Drawings
                            A1                B1                C1            C4
                            A2                B2                C2            C5
                            A3                B3                C3            C6
                    Appendix B:
                            Construction Quality Assurance Plan Table of Contents
                            Introduction
                            Project Organization and Responsibilities
                            Construction
                            Remedial Action Construction
                            Documentation and Reporting
                            References
                            Tables - Construction Submittals
                            Figure 1
                            Figure 2
                            Figure 3
                            Figure 4
                    Appendix C:
                            Table of Contents
                            Introduction
                            Roles and Responsibilities
                            Routine Monitoring Events and Table 1
                            Figure 1
                            Remainder of Appendix C
                    Appendix D:
                            Table of Contents
                            Introduction
                            Bathymetric Survey
                            Sediment Sampling and Analysis
                            Quality Assurance Project Plan
                            References
                            Tables 1-3
                            Tables 4-5
                            Figure 1
                            Figure 2
                            Figure 3

Technical Specifications (English only)
                    Table of Contents
                    Part A General Conditions
                    Part B Technical Specifications

Document Archives

Related Information

Additional Resources

 

map showing site location as Spokane County, WA SITE INFORMATION

Facility Site ID: # 65178472

Location:
Spokane County

Contacts:
Zachary Hedgpeth, Site Manager
(509) 329-3484

Carol Bergin,
Community      Involvement
(509) 329-3546

Status: Ranked, Remedial Action in Progress Get definitions of Status terminology