Rayonier Mill Cleanup Progress

Agreed Order
Tasks


Notes


Completed?

 1  Draft work plan for upland data collection Ecology approved the work plan on August 10, 2010.

Icon:  CheckedBox

 2  Final Work Plan Ecology approved the work plan on August 10, 2010.

Icon:  CheckedBox

 3  Draft tech memo -- upland data summary report The tech memo will give Ecology a chance to see the sampling results before the full report is produced.

Icon:  CheckedBox

 4  Completed Harbor Sediments Investigation (Ecology) Ecology will hold a public comment period on this study later on.  
 5  Agency Review Draft (ARD) upland data summary report This report will incorporate data from Rayonier’s upland sampling.  
 6  ARD marine data summary report This report will incorporate data from Ecology’s Harbor Sediments Study.  
 7  Public Review Draft (PRD) marine data summary report This document will be made available to the public, but the formal comment period will be held later.  
 8  Preliminary cleanup standards These will be based on preliminary cleanup levels Ecology determines from the Harbor Sediments Study.  
 9  PRD upland data summary report This document will be made available to the public, but the formal comment period will be held later.  
 10  Draft interim action alternatives Rayonier will identify a range of cleanup technologies for soil, groundwater, and sediment contamination. They will then see which are feasible to use, and submit them to Ecology.  
 11  ARD alternatives and data summary reports Rayonier must consider cleanup options for the Study Area that: don’t preclude future cleanup of the whole site; meet state cleanup law; and can include habitat restoration.  
 12  Public comment on alternatives and data summary reports This is your chance to provide comments on the cleanup options. The two data reports will provide the information needed to evaluate each option.  
 13  Draft final documents After the public comment period, Rayonier must revise and resubmit the two data reports and the alternatives evaluation.  
 14  ARD Interim Action Plan The last task in the current Agreed Order is to draft a plan for partial cleanup that includes soil, groundwater, and sediments within the Study Area.  
When all tasks are completed, Ecology will negotiate a new Agreed Order for actual cleanup of the Study Area.


* Agreed Order signed by Ecology March 25, 2010.



 











Legend:
ARD = Agency Review Draft
PRD = Public Review Draft
        Marine
        Upland
        Alternatives Evaluation
        Interim Action Plan