Port Angeles Rayonier Mill Site



March 2012 Agreed Order Timeline Update  

We have revised our estimated timeline for drafting a cleanup plan for the Study Area.  Rayonier is still on schedule with their Agreed Order tasks.  However, the work will take longer than we thought because the next steps rely on a report that is not yet complete.  Rayonier needs Ecology to finalize the Port Angeles Harbor Sediments Investigation report so it can finish the Marine Data Summary Report.  This means that the Agreed Order work will likely finish in late 2014 instead of the end of 2013. 