|

|
History
-
Sullivan Dam and
small dam downstream (Mill Pond Dam) constructed in 1911.
-
Small hydroelectric
power plant (4MW) also constructed in 1911 and operated until 1956.
-
Pend Oreille PUD
purchased the project in 1959, including water rights and water
storage rights, and obtained a FERC License, but power was never
generated by the District.
-
Project has been
operated as directed in FERC License. FERC License is expiring and
District plans to surrender the FERC License.
|
|
|
Current Sullivan Lake Operation
-
Sullivan Lake fills
and empties each year in accordance with Pacific Northwest
Coordination Agreement and its existing FERC license.
-
The lake begins to
fill each spring about April 1
-
To the extent
possible, the lake maintains a constant full elevation of 2,588.6
for the months of June through September for summer recreation. The
gates on the dam are opened October 1 to begin lowering the lake to
provide room to catch spring run-off and provide downstream power
benefits.
-
Lake is drained to
elevation 2565.0 by about December 15 each year.
-
Minimum instream flow
release of 10 cfs (of inflow, if lower) is maintained year-round. •
US Forest Service has campgrounds and boat launches on Sullivan
Lake. • Flows at the dams are monitored. Gates are adjusted and
maintained. Five-year dam safety inspections are conducted as part
of the FERC License.
|
Issues and Concerns
When Sullivan Dam FERC License was surrendered, therewas an
opportunity to change project operations. Some of the issues of concern
to agencies and the public include:
-
Desire to improve
fishery in Sullivan Creek. Sullivan Creek has been identified as
potential bull trout recovery habitat;
-
Desire to minimize
water temperature increases during lake draining;
-
Whitewater recreation
enthusiasts desire flows in 200cfs range for optimum kayaking during
lake draining;
-
Desire to maintain
lake full or near full in summer for recreation and for docks owned
by local cabin owners;
-
Desire to increase
minimum instream flow releases;
-
Desire to avoid rapid
increases or decreases in dam discharge flows;
-
Desire to control
costs of new measures;
-
Boundary Dam
(downstream of Sullivan) is in FERC relicensing and Seattle City
Light is interested in potential mitigation projects.
To address the issues,
stakeholders participated in settlement discussions beginning in
September 2009. Participants included:
| • Pend Oreille PUD |
• Seattle City Light |
| • US Forest Service |
• Kalispel Tribe |
| • Ecology |
• WA Dept of Fish &
Wildlife |
| • USFWS |
• American Whitewater |
| • The Lands Council |
• Members of the public |
Settlement was reached in
February 2010 and was submitted to FERC and US Forest Service for
environmental review and approval. WDOE 401 application
|
Operational Changes
-
Instream flow
releases increased from 10 cfs to 60 cfs in June, to 30 cfs in July
and August.
-
Lake draining started
sooner (day after Labor Day instead of October 1).
-
Lake draining target
elevation increase from 2565.0 to 2570.0 (5 feet less drawdown).
-
Water temperatures
and flows monitored and releases adjusted to avoid downstream
temperatures over 16C.
-
Cold water release
pipe will be constructed to allow dam discharges to come from deep
in the lake, with cooler water.
-
Mill Pond dam will be
decommissioned and removed.
-
Flow rate changes
will be controlled to meet agreed upon flow ramping rates.
As a result of revising the operations at Sullivan Lake, most of the
identified issues are addressed. Additional flows are released from
current situation as follows:
-
June-50 cfs average
increase-3,000 ac-ft additional release in June
-
July and August-20
cfs average increase-1200 ac-ft additional release per month (2,400
total)
-
September-previously
only 10 cfs released. Now expect average year releases to be 150 cfs
all month –about 9,000 ac-ft
-
Total new releases
June 1-Sept. 30 = 14,400 ac-ft
|
|
|
|
|
|
|
Copyright © Washington State Department of Ecology. See http://www.ecy.wa.gov/copyright.html.