September 1998 - Entire team assembled
September - February 1999 - Model development
March - May - Synthesis work
June 15th - First Draft methods document completed
June 16th - Document mailed to selected per reviewers
July 31st - Home page active
August 1st - First Draft comments due-
Establish Snohomish technical work team
August 15th - All data and metadata available on home page
September 1st - Revisions made to first draft
September 15th - Revised draft methods document available for review
November 1st - Revised draft comments due
August - December - Snohomish technical work team develops & evaluates sub-basin scale assessment methods
December - Re-establish Ecology watershed characterization team
January-June, 2000 - River basin characterization in Lewis River Basin (WRIA 27 - tentative)